S1296......................................................by STATE AFFAIRS
CAPITOL CONSTRUCTION - Adds to existing law to provide for the
prequalification of contractors and subcontractors on capitol building
construction and renovation projects; and to provide conditions if
prequalification is used.
01/17 Senate intro - 1st rdg - to printing
01/18 Rpt prt - to St Aff
01/24 Rpt out - rec d/p - to 2nd rdg
01/25 2nd rdg - to 3rd rdg
01/29 3rd rdg - FAILED - 14-18-3
AYES--Andreason, Bunderson, Darrington, Deide, Geddes, Lodge, Noh,
Richardson, Risch, Sandy, Sorensen, Stegner, Thorne(Thorne), Wheeler
NAYS--Boatright, Branch, Burtenshaw, Cameron, Davis, Dunklin,
Frasure, Goedde, Hawkins, Hill, Ipsen, Keough, King-Barrutia, Little,
Marley, Schroeder, Stennett, Williams
Absent and excused--Brandt, Ingram, Sims
Floor Sponsor - Darrington
Hld for reconsideration
01/31 Vote to Reconsider - FAILED - 13-22-0
To Secretary of Senate
|||| LEGISLATURE OF THE STATE OF IDAHO ||||
Fifty-sixth Legislature Second Regular Session - 2002
IN THE SENATE
SENATE BILL NO. 1296
BY STATE AFFAIRS COMMITTEE
1 AN ACT
2 RELATING TO THE PREQUALIFICATION OF CONTRACTORS AND SUBCONTRACTORS; AMENDING
3 CHAPTER 57, TITLE 67, IDAHO CODE, BY THE ADDITION OF A NEW SECTION
4 67-5711E, IDAHO CODE, TO PROVIDE FOR THE PREQUALIFICATION OF CONTRACTORS
5 AND SUBCONTRACTORS ON CAPITOL BUILDING CONSTRUCTION AND RENOVATION PROJ-
6 ECTS, AND TO PROVIDE CONDITIONS IF PREQUALIFICATION IS USED; DECLARING AN
7 EMERGENCY; AND PROVIDING A SUNSET DATE.
8 Be It Enacted by the Legislature of the State of Idaho:
9 SECTION 1. That Chapter 57, Title 67, Idaho Code, be, and the same is
10 hereby amended by the addition thereto of a NEW SECTION, to be known and des-
11 ignated as Section 67-5711E, Idaho Code, and to read as follows:
12 67-5711E. CAPITOL BUILDING CONSTRUCTION AND RENOVATION PROJECTS --
13 PREQUALIFICATION. With respect to any contract to be entered by the director
14 of the department of administration or his designee for capitol building con-
15 struction and renovation projects, and any part thereof, the administrator of
16 the division of public works may require contractors and subcontractors to be
17 prequalified. If prequalification is used, the following conditions shall
18 apply:
19 (1) Adequate public notice of the prequalification process, including the
20 written criteria and procedures for prequalification, shall be given at least
21 fourteen (14) days prior to the date prequalification applications are due
22 including publication in a newspaper of general circulation in the area where
23 the work is located, and shall include instructions on the prequalification
24 application process;
25 (2) Only contractors and subcontractors licensed in Idaho to perform pub-
26 lic works contracts shall be eligible for prequalification;
27 (3) At least five (5) or more general contractors and subcontractors
28 shall be prequalified for the construction or renovation project or applicable
29 part thereof. However, if less than five (5) contractors or subcontractors
30 request to be prequalified or if less than five (5) contractors or subcontrac-
31 tors meet prequalification requirements, then only that number shall be pre-
32 qualified;
33 (4) Prequalification determinations shall be based on written criteria
34 and procedures established by the administrator of the division of public
35 works and approved by the permanent building fund advisory council;
36 (5) Following the prequalification determination, competitive sealed bid-
37 ding shall be accomplished in accordance with the provisions of section
38 67-5711C, Idaho Code; and
39 (6) When the prequalification process is used, only prequalified contrac-
40 tors shall be permitted to bid. If the contractor is submitting as a general
41 contractor, its subcontractors named must also be prequalified.
42 SECTION 2. An emergency existing therefor, which emergency is hereby
2
1 declared to exist, this act shall be in full force and effect on and after its
2 passage and approval.
3 SECTION 3. The provisions of Section 1 of this act shall be null, void
4 and of no force and effect on and after June 30, 2008.
STATEMENT OF PURPOSE
RS 11426C2
Idaho's capitol building is a significant public monument,
symbolizing Idaho's sovereignty and the spirit of Idaho's
citizens. The capitol building is one of Idaho's most renowned
landmarks. The Idaho Legislature has recognized the importance
of the capitol building by the creation of the Idaho state capitol
commission and the funding of the capitol renovation project.
This legislation will allow the Department of Administration,
Division of Public Works to require contractors and subcontractors
to be pre-qualified in their area of work in order to bid or be
included in bids for work on the capitol building, where a contract
is to be entered by the director of the Department of Administration
or his designee. The purpose is to ensure that the renovation work
is done by craftsman and contractors with the skills necessary to
successfully complete the required work in a timely fashion.
FISCAL IMPACT
No fiscal impact to the General Fund.
CONTACT
Name: Joanna L. Guilfoy
Deputy Attorney General
Agency: Department of Administration
Phone: 332-1832
Statement of Purpose/Fiscal Impact S 1296