Print Friendly

     Idaho Statutes

Idaho Statutes are updated to the website July 1 following the legislative session.

pecnv.out

TITLE 61
PUBLIC UTILITY REGULATION
CHAPTER 6
PROCEDURE BEFORE COMMISSION AND IN COURTS
61-642.  Overcharge — Recovery of payment. If the public utility does not comply with the order for the payment or reparation within the time specified in such order, suit may be instituted in any court of competent jurisdiction to recover the same. All complaints concerning excessive or discriminatory charges shall be filed with the commission within three (3) years from the time the cause of action accrues, and the petition for the enforcement of the order shall be filed in the court within one (1) year from the date of the order of the commission. The remedy in this section provided shall be cumulative and in addition to any other remedy or remedies in this act provided in case of failure of a public utility to obey an order or decision of the commission.

History:
[(61-642) 1913, ch. 61, sec. 67b, p. 248; reen. C.L. 106:148; C.S., sec. 2516; I.C.A., sec. 59-642; am. 1965, ch. 215, sec. 1, p. 498.]


How current is this law?